New E8 and Ramfjord Bridge - tour and presentation of the project

Lifting of steel box to bridge. Photo: Norwegian Public Roads Administration
Photo: Norwegian Public Roads Administration

870 meters of beam bridge – join an exciting professional tour. We will hear more about the development of Tromsø's new access road and get close to the Ramfjord Bridge.

Lifting of steel box to bridge. Photo: Norwegian Public Roads Administration
Photo: Norwegian Public Roads Administration

Signup

New E8 and Ramfjord Bridge - tour and presentation of the project

The Norwegian Public Roads Administration is building an approximately 10-kilometer new E8 between Sørbotn and Laukslett. The new road will provide a shorter, safer, and more accessible access road to Tromsø, while also contributing to better traffic safety and living conditions along the current E8 through Ramfjord.

We receive a professional briefing about the project and a tour of the construction site.
The project has several bridges, including the bridge over Ramfjorden. It is made of reinforced concrete with a steel superstructure, and has a length of 870 meters. The bridge has five main spans of 135 meters and side spans. Five foundations are piled from barges, each up to 80 meters long. The superstructure is divided into seven sections for lifting, with the heaviest lifting around 900 tons. In autumn 2025, assembly began on the large steel boxes that will support the road surface and traffic across the fjord.


The event is suitable for those curious about bridge and road construction, large transport projects, and how complex construction projects are carried out in practice.


Practical information about the meeting place, clothing, and how to conduct the tour will be provided closer to the event.

Renate Bakkehaug

Senior Advisor